Current projects Plant engineering and construction

Mallorca, Spain

Client: TIRME
Type and size of plant: Expansion of the capacity about ca. 25.000 t/a
Project scope: Engineering, supply and erection of mechanical and process equipment as well as start up of anaerobic digestion plant.
Applied technology: feedstock preparation in a hammer separation mill, wet digestion process in the LARAN® loop digester
Realisation period: 2018 - 2019

Carboli, Italien
Client: ATZWANGER AG
Plant type and capacity: anaerobic dry digestion of 20.000 t/a bio waste
Project scope: Engineering, delivery, installation and start up of the entire electrical and mechanical part of the dry digestion plant
Applied technology: anaerobic dry digestion with one LARAN® plug flow digester TF1400
Realisation period: 2018 - 2019

Beddizole, Italien
Client: ATZWANGER AG
Plant type and capacity: anaerobic dry digestion of 60.000 t/a bio waste
Project scope: Engineering, delivery, installation and start up of the entire electrical and mechanical part of the dry digestion plant
Applied technology: anaerobic dry digestion with two LARAN® plug flow digester TF2100
Realisation period: 2018 - 2019

Middenmeer, Netherlands
Client: N.V. HVC from Alkmaar
Type and size of plant: Expansion of the existing bio waste digestion plant from 80.000t/a to 110.000 t/a
Project scope: Engineering, procurement and construction and start up of the entire digestion plant
Applied technology: anaerobic dry digestion with LARAN® plug flow digester TF2200
Realisation period: 2017 - 2018

Arcis, France
Client: JV of SCARA and Naskeo Environnement
Plant type and capacity: anaerobic dry digestion of 42.500 t/a agricultural waste products
Applied technology: anaerobic dry digestion with LARAN® plug flow digester TF2500
Realisation period: 2017 - 2019

Loiret, France
Client: BGB Loiret
Plant type and capacity: anaerobic dry digestion of 25.000 t/a agricultural waste products
Applied technology: anaerobic dry digestion with LARAN® plug flow digester TF1900
Realisation period: 2017 - 2019

Carpi, Italien
Client: ATZWANGER AG
Plant type and capacity: anaerobic dry digestion of 41.000 t/a bio waste
Project scope: Engineering, delivery, installation of the mechanical and electrical part / automation, as well as commissioning of the digestion
Applied technology: anaerobic dry digestion with LARAN® plug flow digester TF2800
Realisation period: 2017 - 2019

Anzio, Italien
Client: ATZWANGER AG
Plant type and capacity: anaerobic dry digestion of 40.000 t/a bio and geen waste
Project scope: Engineering, delivery, installation of the mechanical and electrical part / automation, as well as commissioning of the digestion
Applied technology: anaerobic dry digestion with LARAN® plug flow digester TF2600
Realisation period: 2017 - 2019

Ploiesti, Romania
Client: Ploiesti County Council
Plant type and capacity: Mechanical-biological waste treatment plant with a capacity of 150.000 t/a
Project scope: Turnkey construction of a waste treatment centre
Contract value: approx. EUR 11,5 million
Applied technology: Mechanical waste processing, sorting plant for the recovery of secondary raw materials, aerated intensive composting with membrane/cover in boxes, open windrow composting
Realisation period: 2017 - 2018

Ljubljana, Slovenia
Client: Municipality of Ljubljana, represented by SNAGA d.o.o.
Plant type and capacity: Mechanical-biological waste treatment plant with a capacity of 171,200 t/a, with integrated biowaste treatment for 30,000 t/a
Project scope: New construction of a turnkey plant (design and build) as general contractor
Contract value: EUR 112 million
Applied technology: Deep bunker; mechanical processing for different types of waste; sorting/recovery of secondary raw materials; fuel processing and production (RDF); dry digestion with 3-stage digestate dewatering; modular box composting; 2-stage exhaust air treatment, biogas utilisation in CHP plants
Realisation period: 2012 - 2018

Liège, Belgium
Client: INTRADEL
Plant type and capacity: Biowaste treatment plant with a capacity of 40,000 t/a
Project scope: Construction of a turnkey plant (design and build) as general contractor
Contract value: EUR 27.5 million
Applied technology: Dry digestion; thermal drying of the digestate; post-composting of the dried digestate (separate location); compost refining; 2-stage exhaust air treatment
Realisation period: 2014 - 2019